As of 2025-12-22, 42 development projects have been reviewed by City of Edmonton's building-permit process in the Clover Bar Area area. 37 are new builds, and 42 are currently advancing. Use types: 3 commercial.
Recent activity
To construct Exterior and Interior Alterations to an existing General Industrial Use Building. Scope of work only on Bay 3 to create 3 new levels. Level 1&2 shell space and Level 3 Offices. "EPCOR Integrated Operations Center-Building 1" SEPARATE PERMIT REQUIRED FOR TEMPORARY ASSEMBLY SPACE.
To construct a utility building (landfill gas control building) - Clover Bar Landfill, Edmonton Waste Management Centre.
To construct a TEMPORARY structure (100' x 50'- metal side walls/fabric covered roof) structure for STORAGE ONLY - Rebel Heart Trucking. NOTE: permit expires Sep 2, 2029.
To move onsite a 9.3 m2 (100 ft2) non-heated pre-fab steel utility (electrical) building. NOTE: Existing without permits
To construct a new commercial (steel fabricated) utility building (electrical substation building) for the ENZHEC project. - Air Products Canada Ltd
Projects (42)
To construct Exterior and Interior Alterations to an existing General Industrial Use Building. Scope of work only on Bay 3 to create 3 new levels. Level 1&2 shell space and Level 3 Offices. "EPCOR Integrated Operations Center-Building 1" SEPARATE PERMIT REQUIRED FOR TEMPORARY ASSEMBLY SPACE.
To construct a utility building (landfill gas control building) - Clover Bar Landfill, Edmonton Waste Management Centre.
To construct a TEMPORARY structure (100' x 50'- metal side walls/fabric covered roof) structure for STORAGE ONLY - Rebel Heart Trucking. NOTE: permit expires Sep 2, 2029.
To move onsite a 9.3 m2 (100 ft2) non-heated pre-fab steel utility (electrical) building. NOTE: Existing without permits
To construct a new commercial (steel fabricated) utility building (electrical substation building) for the ENZHEC project. - Air Products Canada Ltd
To construct a new commercial warehouse building. --Fort Garry Industries Aurum--
To construct a General Industrial Building (ISLZ Logistics Ltd.) located in outside ten minutes area. Outside 10 minute response time.
To Demolish a General Industrial Use Building (Plant and Warehouse) and multiple Accessory Buildings and Structures
To construct a mixed-use industrial building (F1, F2, and D use with four (4) -4HR firewalls located currently in OUTSIDE 10 minutes response area) - "Western Midstream shop and office"
To construct an industrial building (cold storage building 32.40m x 38.25m), - Kleysen Group, salt storage shed.
To construct an addition ( 2100 sqft; a new testing bay) to a General Contractor building (TAHK Projects Ltd.).
To construct an accessory building (Compressor building) to a Major Impact Utility Service (Enerkem Alberta Biofuels).
To construct a Gas Bar for Atco Gas (Adding a Canopy for fueling of Compressed Natural Gas vehicles - 2 dispenser, 1 x 30*44' canopy with 4 columns) "Clean Energy Fuels"
To construct a new commercial building (6 unit office trailer complex) - Worleycord.
Construction of a new Industrial building. New Truck Loading Building for transportation of RDF materials for the City of Edmonton's Edmonton Waste Management Centre.
To construct interior alteration to an existing Composting Facility. SSO Pre-Processing Equipment Reconfiguration, "Anaerobic Digestion Facility. Edmonton Waste Management"
To Construct a new general industrial building.
To construct a General Industrial Use Building (Administrative office trailer for a trucking company) -DCT Chambers Trucking Ltd.
To construct a new commercial building (move on modular office/change room , units are AltaFab CSA certified new units) - Edmonton Waste Management, CURE site offices.
To construct and operate a minor impact utility service building (Aurum Road Sanitary Pump Station)
To construct a General Industrial Use (maintenance and office) building. New 4 story maintenance building with offices, storage area and paint spray booth. Also to demolish 2 metering stations and pipe trench.
To construct an addition to a Cold Storage Accessory building, two independent free standing structures, collectively one building area and classification. Identified as a Compressor, PPE Storage and Electrical Services storage and to demolish a pre-existing structure, collectively under a single permit.
To construct a two storey General Industrial Use (F2) building for Re-Em Transport, A 4 hour pre-cast fire wall between the shop (Building A) and carwash (Building B), 2 Barrier free washrooms, 2 make up air units, 2 roof top units, 1 Mezzanine with 2 - 1Hr rated stairwells.
To construct an industrial building - Visco Demolition, shop and office.
To construct interior and exterior alterations to an existing warehouse building and to demolish existing tank farm. Fit up existing shell office floor area for main, second, and third floor offices, install new Fire suppression system in the F2 portion of the building, replace existing tilt up panels with steel construction walls and insulated metal panels, add windows on south and east wall and move the existing exterior unenclosed stairwell from south to the east side, erect fire wall between F1 and F2 buildings.
To construct a General Industrial Use building. Eng-Con New Facility
To construct an accessory storage structure, and temporarily store a site trailer on the site. (Maximum of 2 Years).
To construct a utility building for electrical instrumentation controls and software - Pembina Pipeline.
To construct a power utility building (Cooling Auxilary building) to a Major Impact Utility Services Site.
To construct a 9m x 21m pump house accessory building to an existing General Industrial Use Site.
To construct front & rear additions to an existing General Industrial Use building (two storey front office addition and rear warehouse shop addition).
To construct a General Industrial use building with Accessory offices (Co-op propane facility).
To construct an accessory building (12m x 20m tent) to a Major Impact Utility Service Site (Edmonton Waste Management Centre)
To construct a General Industrial storage building as part of a three building development (Tool Crib).
To construct an addition to the existing General Industrial Use building Gilead (Phase 2); laboratory addition.
To construct a General Industrial Use building (1 Storey with Accessory offices).
To construct an Industrial building - Shop and Office Building-GIBSONS ENERGY.
To construct a General Industrial Use building (2 bays, with mezzanine) ("Capital Truck Body & Equipment")
To construct an industrial building "Tremcar West" BUILT WITHOUT PERMITS.
To construct a Supernatant Treatment Facility (Nutrient Recovery Facility for Epcor Water Services) - 27 m2 Mezz, Service Platforms.
To construct an Ancillary Use building (equipment storage and maintenance facility).
To construct an Accessory building (office / control building) to an existing General Industrial Use (ALBERTA DILUENT TERMINAL)