500, 250 Aurum Road NE — development project
This industrial project (new construction) at 500, 250 Aurum Road NE, in the Clover Bar Area neighbourhood, has been the subject of 8 applications before City of Edmonton's building-permit process between 2016-02-04 and 2021-02-02. Estimated construction value: $5.6M. Status: advancing — latest status: Issued. Application types: New — Commercial Final, Exterior Alterations — Commercial Final.
Location & nearby projects
● this project · ○ nearby projects — click a dot to open its page
Filing history (8)
2021-02-02 — New — Commercial Final
· Issued (3-363261805)
Construction of a new Industrial building. New Truck Loading Building for transportation of RDF materials for the City of Edmonton's Edmonton Waste Management Centre.
2020-09-24 — New — Commercial Final
· Issued (6-363261805)
Construction of a FOUNDATION ONLY for a new Industrial building. New Truck Loading Building for the City of Edmonton's Edmonton Waste Management Centre.
2020-07-20 — Exterior Alterations — Commercial Final
· Issued (3-339329344)
To construct alterations to a Commercial General Industrial use building. Addition of a ventilation system for the Tip Floor. Project involves the installation of 3 new dry scrubbers, concrete slab on grade, housekeeping pad, civil works, associated ducting and supports, patching of existing building envelope and roof, electrical work and instrumentation/ controls. The work includes partial removal of existing ductwork on the Tip Floor roof as well as removal of an existing concrete apron slab and bollards.
2020-03-27 — New — Commercial Final
· Issued (7-342396483)
To Construct a new building - HSADF Post Commissioning Upgrades - Heated enclosure around existing machinery
2017-09-14 — Exterior Alterations — Commercial Final
· Issued (3-242795625)
To construct interior (RDF Dryer and equipment) / exterior (create openings in an existing building for mechanical equipment) alterations, concrete slab for a new dryer stack and install an underground sewage tank for a Special Waste Transfer Facility (Edmonton Waste Management Centre).
2017-09-14 — New — Commercial Final
· Issued (4-242795625)
To construct construct an Accessory boiler building for Waste Transfer Facility (Edmonton Waste Management Centre).
2017-06-13 — New — Commercial Final
· Issued (2-237307985)
To construct an Ancillary Use to Waste Management Operations building (concrete bunker for wood chips storage, 20m x 32m)
2016-02-04 — New — Commercial Final
· Issued (3-172281704)
To construct the Secant Pile Wall SHORING ONLY for an addition to an existing Composting Facility. Anaerobic Digestion Facility.
Other projects in Clover Bar Area
To Demolish a General Industrial Use Building (Plant and Warehouse) and multiple Accessory Buildings and Structures
To construct a General Industrial Use (maintenance and office) building. New 4 story maintenance building with offices, storage area and paint spray booth. Also to demolish 2 metering stations and pipe trench.
To Construct a new general industrial building.
To construct an addition to a Cold Storage Accessory building, two independent free standing structures, collectively one building area and classification. Identified as a Compressor, PPE Storage and Electrical Services storage and to demolish a pre-existing structure, collectively under a single permit.
To construct an addition to the existing General Industrial Use building Gilead (Phase 2); laboratory addition.
To construct a General Industrial Building (ISLZ Logistics Ltd.) located in outside ten minutes area. Outside 10 minute response time.
To construct an accessory storage structure, and temporarily store a site trailer on the site. (Maximum of 2 Years).
To construct a TEMPORARY structure (100' x 50'- metal side walls/fabric covered roof) structure for STORAGE ONLY - Rebel Heart Trucking. NOTE: permit expires Sep 2, 2029.