5030 127 Avenue NW — projet de développement
Ce projet commercial (construction neuve) situé au 5030 127 Avenue NW, dans le quartier Kennedale Industrial, a fait l'objet de 2 demandes devant le processus de permis de construction de la Ville d'Edmonton entre le 2018-08-21 et le 2019-05-27. Valeur estimée des travaux : $715K. Statut : en progression — dernier statut : Issued. Types de demande : New — Commercial Final, Addition — Commercial Final.
Emplacement et projets à proximité
● ce projet · ○ projets à proximité — cliquez sur un point pour ouvrir sa fiche
Historique des demandes (2)
2019-05-27 — Addition — Commercial Final
· Issued (4-303504511)
To construct an Addition (111 m2)to an existing Commercial building (Includes opening portion of West exterior wall, constructing a ramp and two overhead doors for loading dock bay, add new overhead door on the south elevation, and Facade Improvement).
2018-08-21 — New — Commercial Final
· Issued (9-273976535)
To construct a commercial building, 50th Street Commercial. 1 Demising Walls rated for 2 hours, 4 Roof Top Units, No Washrooms, Shell only.
Autres projets dans Kennedale Industrial
To construct interior and exterior alterations to convert a commercial building to a mixed use commercial building (Mercantile, Business and Personal Service, Assembly, Residential, Parking Garage). 15 RTU's 1st Floor - Work/Living Units 1-13 complete, CRU 1 Restaurant (existing, No changes being made), CRU 2,3,4,5 SHELL ONLY Require Separate permits for tenant fit up 2nd floor- Work/Living Units 2-13 complete, Unit 205 (New Psychology), Unit 202(dentist), Unit 208(Denture Clinic) existing selective demo for HVAC, sprinkler, and fire alarm upgrades. Unit 213 (Existing Psychology) Units 206, 220, 221 Require separate permits for tenant fit up
To construct an addition to a Minor Impact Utility Service building (Epcor). 2 RTU's on roof. 1 Storey addition with basement
To construct a General Industrial use storage building.
To construct a general Industrial use shell building, "Vinton Carpets"; (no washroom, 2 unit heater)
To construct a new General industrial building - F-3. Non-Combustible Storage/Workshop for RTM Electrical
To construct a General Industrial Use building containing 10 suites w/ mezzanines (Palermo Building)
To construct a two-storey addition (455.22 sq.m.) and interior alterations to an existing General Industrial building.
To construct a General Industrial Use building. "Nortalta integrated services limited"