11403 174 Street NW — projet de développement
Ce projet commercial (agrandissement) situé au 11403 174 Street NW, dans le quartier Armstrong Industrial, a fait l'objet de 1 demande devant le processus de permis de construction de la Ville d'Edmonton lors de la séance du 2025-01-27. Valeur estimée des travaux : $990K. Statut : en progression — dernier statut : Issued. Type de demande : Addition — Commercial Final.
Emplacement et projets à proximité
● ce projet · ○ projets à proximité — cliquez sur un point pour ouvrir sa fiche
Historique des demandes (1)
2025-01-27 — Addition — Commercial Final
· Issued (5-510228163)
To construct an Addition to an existing industrial use building (3 bay addition). "Calmont Volvo"
Autres projets dans Armstrong Industrial
To construct an addition to an Industrial building (UAP/NAP warehouse) and exterior alterations (additional loading doors, parking stalls along the West façade, adjustments required to NE of the existing sodded area to allow the additional loading parking stalls and emergency fire truck access). *** Storage racking requires a separate permit.
To construct an addition to an Automotive/Minor Recreation Vehicle Sales/Rentals building A (4 Bays used for Windshield Repair and Vehicle delivery, Lexus).
To construct a storage tent addition (cold storage) - Atlantis Marine.
To change the Use to a Professional, Financial and Office Support Services Use and to construct additional floor areas on the second floor and interior alterations within Bay 1.
To construct Interior and exterior Alteration to an existing warehouse - 2019 EDMONTON DC2 HALL 7 & 8 EXPANSION - Expansion of Rogers data center within empty warehouse.
To construct exterior alterations to an existing minor industrial building (addition to a cold storage building with no mechanical or heating systems (unconditioned space)) with no changes to the existing building's interior and exterior. -- Consolidated Gypsum -- *Storage racking requires a separate permit.
To construct an Addition (3,799.00 sqm expansion) to a General Industrial Use Building and Exterior Alterations to the Site (Centre 118). No RTU's No Washrooms / structural for future RTUs provided and 2 Hr exit corridor