10850 104 Avenue NW — projet de développement
Ce projet institutionnel (rénovation) situé au 10850 104 Avenue NW, dans le quartier Downtown, a fait l'objet de 7 demandes devant le processus de permis de construction de la Ville d'Edmonton entre le 2018-03-28 et le 2026-04-23. Valeur estimée des travaux : $19.2M. Statut : en progression — dernier statut : Issued. Types de demande : Addition — Commercial Final, Interior Alterations — Commercial Final, Exterior Alterations — Commercial Final.
Emplacement et projets à proximité
● ce projet · ○ projets à proximité — cliquez sur un point pour ouvrir sa fiche
Historique des demandes (7)
2026-04-23 — Exterior Alterations — Commercial Final
· Issued (2-651039052)
To construct Interior Alterations (convert office/classrooms to student laboratories and support spaces) on the main floor of an existing post-secondary education building (MacEwan University Building 6).
2022-06-29 — Interior Alterations — Commercial Final
· Issued (1-433605348)
To complete Interior Alterations construct new exit stairs in an existing educational assembly building. (Add capacity of 225 people to building 7) - MacEwan University
2020-07-23 — Addition — Commercial Final
· Issued (2-255022891)
To construct a new addition to an existing post secondary education building on the MacEwan City Centre Campus (SAMU Building).
2020-07-17 — Interior Alterations — Commercial Final
· Issued (1-365109629)
To construct alterations to an education assembly building ( MacEwan University Building 5)
2020-01-29 — Interior Alterations — Commercial Final
· Issued (1-345349890)
To construct interior alterations to A2 assembly building - Floors 3-5, tenant improvements to East side of Allard Hall - Grant McEwan U
2020-01-28 — Interior Alterations — Commercial Final
· Issued (1-348024732)
To construct Interior Alteration to the west side of the 5th floor of Allard Hall
2018-03-28 — Addition — Commercial Final
· Issued (9-255022891)
To construct STRUCTURAL FRAME ONLY for the SAMU addition to Grant MacEwan City Centre Campus.
Autres projets dans Downtown
To construct a mixed use high building over existing underground parkade (Main - retail shell, residential amenity, 2nd to 36th- 363 dwelling units) - The Parks, building 1.
To construct a mixed use building (285 Dwellings) 5 storey Podium with West MidRise Tower. Mercantile uses on the main floor, 3rd floor Assembly use, renovation and addition to the existing underground parkade and a pedway connection - Station Lands North.
To construct a STRUCTURAL FRAME ONLY for a 56-storey mixed use tower on podium (Hotel/Residence AC Building)
To construct a mixed-use building on an existing parkade/foundation and existing structural frame, main floor: retail (shell only, no demising walls) with common area and leasing office fit up, floors 2 to 30 common area and residential units (240 dwellings) - The Augustana.
To construct an multi-use building (main floor retail, upper floors residential apartments) - Mayfair North.
To construct a 29 Storey Apartment building (240 Dwellings) with amenity space on level 02. Two general retail of SHELL ONLY (cru-1, cru-2) on the main floor and 5 underground parking levels - Falcon Tower One.
To construct a multi-use high building with underground parkade, retail/office/parking: floors 1-4; Residential: floors 6-33. Fox 2 (South Tower).
To change the use of main floor retail stores to eleven (11) new live/work units and construct interior and exterior alterations - Center West.